-Full replacement of the old system that consists of 75 chiller of 5 Ton Refrigeration each, with a central station that provides all the buildings with chilled water with a total cooling capacity of 400 Ton Refrigeration (nominal capacity), using direct fired absorption chillers.

    • Project execution phases

This project is executed on three phases:

- phase 1 200 TR

- phase 2 100 TR

- phase 3 100 TR

    • The HVAC cost:

4.3 million Egyptian pounds.

    • GasCool scope of work:

Basic design, detailed engineering, construction supervision and start up for HVAC system equipment.